Skip to content
Daily Progress Report
JOB SUPERVISOR: This form is a single-day report. Complete the report and email a copy to yourself, the Project Manager, and any other interested stakeholder.
DAILY PROGRESS REPORT
Project
Builder
Date
Time
By Site Supervisor
Site Supervisor Email
Copy to
Copy to
Supervisor Summary
Supervisor On Site
Supervisor Left Site
Project Schedule
Ahead of schedule
On schedule
Behind schedule
Conditions
Temperature
Over 100°
80° - 100°
50° - 79°
32° - 49°
Below 32°
Weather
Sunny
Windy
Overcast
Foggy
Rain
Snow
Sleet
Safety Issues on Site
Safety Issue
Photo
Action Taken
Safety Issue
Photo
Action Taken
Safety Issue
Photo
Action Taken
Visitors On Site
Visitor
Client
OSHA
Building Inspector
Trade Inspector
Supplier
Other
Work Phase
Work Site
Excavation
Foundation
Framing Labor
Framing Labor: Deck-Porch
Framing Labor: Stairs
HVAC
Plumbing: Slab-on-Grade
Plumbing: Crawlspace
Electrical
Fireplace
Window-Exterior Door Install
Roofing
Siding-Exterior Trim
Brick Veneer
Stone Veneer
Concrete Flatwork
Stucco
Garage Door
Shutters
Gutters
Painting
Insulation
Drywall
Finish Carpentry
Floor Coverings
Surrounds
Cabinet Install
Countertops Install
Mirrors - Shower Doors
Trim Hardware Install
Cleaning
Landscaping
Comments
Inspection Results
Approved
Pass
Conditional Pass
Fail
Visitor
Client
OSHA
Building Inspector
Trade Inspector
Supplier
Other
Work Phase
Work Site
Excavation
Foundation
Framing Labor
Framing Labor: Deck-Porch
Framing Labor: Stairs
HVAC
Plumbing: Slab-on-Grade
Plumbing: Crawlspace
Electrical
Fireplace
Window-Exterior Door Install
Roofing
Siding-Exterior Trim
Brick Veneer
Stone Veneer
Concrete Flatwork
Stucco
Garage Door
Shutters
Gutters
Painting
Insulation
Drywall
Finish Carpentry
Floor Coverings
Surrounds
Cabinet Install
Countertops Install
Mirrors - Shower Doors
Trim Hardware Install
Cleaning
Landscaping
Comments
Inspection Results
Approved
Pass
Conditional Pass
Fail
Visitor
Client
OSHA
Building Inspector
Trade Inspector
Supplier
Other
Work Phase
Work Site
Excavation
Foundation
Framing Labor
Framing Labor: Deck-Porch
Framing Labor: Stairs
HVAC
Plumbing: Slab-on-Grade
Plumbing: Crawlspace
Electrical
Fireplace
Window-Exterior Door Install
Roofing
Siding-Exterior Trim
Brick Veneer
Stone Veneer
Concrete Flatwork
Stucco
Garage Door
Shutters
Gutters
Painting
Insulation
Drywall
Finish Carpentry
Floor Coverings
Surrounds
Cabinet Install
Countertops Install
Mirrors - Shower Doors
Trim Hardware Install
Cleaning
Landscaping
Comments
Inspection Results
Approved
Pass
Conditional Pass
Fail
Subcontractors on Site
Work Phase
Excavation
Foundation
Framing Labor
Framing Labor: Deck-Porch
Framing Labor: Stairs
HVAC
Plumbing: Slab-on-Grade
Plumbing: Crawlspace
Electrical
Fireplace
Window-Exterior Door Install
Roofing
Siding-Exterior Trim
Brick Veneer
Stone Veneer
Concrete Flatwork
Stucco
Garage Door
Shutters
Gutters
Painting
Insulation
Drywall
Finish Carpentry
Floor Coverings
Surrounds
Cabinet Install
Countertops Install
Mirrors - Shower Doors
Trim Hardware Install
Cleaning
Landscaping
Subcontractor Names
Comments
Work Phase
Excavation
Foundation
Framing Labor
Framing Labor: Deck-Porch
Framing Labor: Stairs
HVAC
Plumbing: Slab-on-Grade
Plumbing: Crawlspace
Electrical
Fireplace
Window-Exterior Door Install
Roofing
Siding-Exterior Trim
Brick Veneer
Stone Veneer
Concrete Flatwork
Stucco
Garage Door
Shutters
Gutters
Painting
Insulation
Drywall
Finish Carpentry
Floor Coverings
Surrounds
Cabinet Install
Countertops Install
Mirrors - Shower Doors
Trim Hardware Install
Cleaning
Landscaping
Subcontractor Names
Comments
Work Phase
Excavation
Foundation
Framing Labor
Framing Labor: Deck-Porch
Framing Labor: Stairs
HVAC
Plumbing: Slab-on-Grade
Plumbing: Crawlspace
Electrical
Fireplace
Window-Exterior Door Install
Roofing
Siding-Exterior Trim
Brick Veneer
Stone Veneer
Concrete Flatwork
Stucco
Garage Door
Shutters
Gutters
Painting
Insulation
Drywall
Finish Carpentry
Floor Coverings
Surrounds
Cabinet Install
Countertops Install
Mirrors - Shower Doors
Trim Hardware Install
Cleaning
Landscaping
Subcontractor Names
Comments
Work Phase
Excavation
Foundation
Framing Labor
Framing Labor: Deck-Porch
Framing Labor: Stairs
HVAC
Plumbing: Slab-on-Grade
Plumbing: Crawlspace
Electrical
Fireplace
Window-Exterior Door Install
Roofing
Siding-Exterior Trim
Brick Veneer
Stone Veneer
Concrete Flatwork
Stucco
Garage Door
Shutters
Gutters
Painting
Insulation
Drywall
Finish Carpentry
Floor Coverings
Surrounds
Cabinet Install
Countertops Install
Mirrors - Shower Doors
Trim Hardware Install
Cleaning
Landscaping
Subcontractor Names
Comments
Work Phase
Excavation
Foundation
Framing Labor
Framing Labor: Deck-Porch
Framing Labor: Stairs
HVAC
Plumbing: Slab-on-Grade
Plumbing: Crawlspace
Electrical
Fireplace
Window-Exterior Door Install
Roofing
Siding-Exterior Trim
Brick Veneer
Stone Veneer
Concrete Flatwork
Stucco
Garage Door
Shutters
Gutters
Painting
Insulation
Drywall
Finish Carpentry
Floor Coverings
Surrounds
Cabinet Install
Countertops Install
Mirrors - Shower Doors
Trim Hardware Install
Cleaning
Landscaping
Subcontractor Names
Comments
Deliveries to Site
What was delivered?
For work phase
Excavation
Foundation
Framing Labor
Framing Labor: Deck-Porch
Framing Labor: Stairs
HVAC
Plumbing: Slab-on-Grade
Plumbing: Crawlspace
Electrical
Fireplace
Window-Exterior Door Install
Roofing
Siding-Exterior Trim
Brick Veneer
Stone Veneer
Concrete Flatwork
Stucco
Garage Door
Shutters
Gutters
Painting
Insulation
Drywall
Finish Carpentry
Floor Coverings
Surrounds
Cabinet Install
Countertops Install
Mirrors - Shower Doors
Trim Hardware Install
Cleaning
Landscaping
What was delivered?
For work phase
Excavation
Foundation
Framing Labor
Framing Labor: Deck-Porch
Framing Labor: Stairs
HVAC
Plumbing: Slab-on-Grade
Plumbing: Crawlspace
Electrical
Fireplace
Window-Exterior Door Install
Roofing
Siding-Exterior Trim
Brick Veneer
Stone Veneer
Concrete Flatwork
Stucco
Garage Door
Shutters
Gutters
Painting
Insulation
Drywall
Finish Carpentry
Floor Coverings
Surrounds
Cabinet Install
Countertops Install
Mirrors - Shower Doors
Trim Hardware Install
Cleaning
Landscaping
What was delivered?
For work phase
Excavation
Foundation
Framing Labor
Framing Labor: Deck-Porch
Framing Labor: Stairs
HVAC
Plumbing: Slab-on-Grade
Plumbing: Crawlspace
Electrical
Fireplace
Window-Exterior Door Install
Roofing
Siding-Exterior Trim
Brick Veneer
Stone Veneer
Concrete Flatwork
Stucco
Garage Door
Shutters
Gutters
Painting
Insulation
Drywall
Finish Carpentry
Floor Coverings
Surrounds
Cabinet Install
Countertops Install
Mirrors - Shower Doors
Trim Hardware Install
Cleaning
Landscaping
Photo Links (max 10)
Send