**SUBCONTRACTOR**
When submitted, form responses are sent to the email addresses provided and then deleted.
TO RETURN THIS SCOPE OF WORK TO THE BUILDER AND/OR TO RETAIN A COPY FOR YOUR FILES,
YOU MUST ENTER THE APPROPRIATE EMAIL ADDRESSES AND SEND.

WINDOW-EXTERIOR DOOR INSTALL
SCOPE OF WORK

Objective of this Scope of Work

► To ensure windows and exterior doors are installed to manufacturer's specifications, are plumb, square, and level, and meets all code requirements.

Terms used in this document

►SITE SUPERINTENDENT: shall refer to any Company representative with authority to enforce this Scope of Work.
►SUBCONTRACTOR: shall refer to the Subcontractor's organization, its employees, or any representative of the Subcontractor assigned the authority to perform per this Scope of Work.

Acceptable Performance
Windows and Exterior Doors may be installed by the Framing Labor Subcontractor, or may be installed by another Subcontractor. In either case, this Scope of Work and the associated Inspection Reports must be completed.
Window and Exterior Door Installation

► A new set of plans is required for each house. Plans are subject to changes and modifications. It is the responsibility of the Subcontractor to have the new plans before beginning work. Plans should be picked up from the Site Superintendent. Any errors that occur from using an incorrect set of plans will be corrected by the Subcontractor at no cost to Company.
► Windows and doors shall be installed per plan and per the manufacturer’s instructions.
► If any framed opening is not correctly sized, or is out of square or not level, and the Subcontractor cannot easily correct the problem, the Site Superintendent should be immediately notified.
► All windows and doors shall be installed so that they are centered in the framed opening and level within 1/16 of an inch.
► All windows and doors shall operate smoothly and correctly.
► Weather-stripping, insulation, and waterproofing shall be installed per the manufacturer’s requirements. Air leakage is unacceptable.
► Flashing shall be installed around all windows as shown in the following installation instructions.
► Flashing shall be installed around all exterior doors. Flashing shall be installed on the bottom of the door first, then the sides of the door overlapping the bottom flashing, then the top of the door overlapping the side flashing. Refer to window flashing video.
► Any items found during the final inspection that need correction shall be corrected before payment will be made.

Send Back to Builder